Tha Maka Irrigation Canal Improvement Project, Phase 5, Benefits 40 Farming Households, Increasing Production and Income.

News No. 98/2025, September 3, 2025

     Ms. Thanyathita Boonmanikul, Deputy Secretary-General of the Office of Agricultural Economics (OAE), revealed the results of the monitoring of the land consolidation and irrigation system project for agriculture, specifically the improvement of the land consolidation area of ​​the Tha Maka Irrigation and Maintenance Project (Phase 5). Ministry of Agriculture and Cooperatives (MOAC) implemented the project to increase the efficiency of water delivery from irrigation canals, enabling water to be distributed evenly across all cultivated plots. This ensures that farmers need in the correct quantity and at the right time, systematically reducing conflicts over water use. Land Consolidation and On-Farm Development Regional Office No. 27 is the main responsible agency, with  target area of ​​1,000 rai.
The project ran from December 2023 and was completed in September 2024.
This was based on field monitoring conducted by the OAE's Evaluation Center.
Last July, in the land consolidation area of ​​Muang Chum Subdistrict, Tha Muang District, Kanchanaburi Province, it was found that the project area had undergone extensive land consolidation several years ago. This had caused the project's irrigation canals to deteriorate over time. Therefore, Land Consolidation and On-Farm Development Regional Office No. 27 undertook the 5th phase of canal improvement. This involved constructing new irrigation canals using compacted soil, excavating the canals, compacting crushed stone, and then lining them with concrete. The canals were constructed with a length of 10,045 meters and included the construction of associated structures for gates to control the water delivery system in the area, as well as 76 sluice gates along the entire length.
This canal improvement has enabled farmers to use water more efficiently for both main-season and off-season rice cultivation.This has benefited farmers in the project area, who have formed a group called the Wai Niao Ruam Jai Phatthana Water Users Group.With a total cultivated area of ​​approximately 1,000 rai, 40 farming households experienced increased yields and net income. The yield of paddy rice increased from 862.32 kg per rai to 919.92 kg per rai (an increase of 57.60 kg per rai, or 6.68%). The yield of dry-season rice increased from 852.55 kg per rai to 855.92 kg per rai (an increase of 3.37 kg per rai, or 0.40%).
This resulted in farmers profit from selling paddy rice increasing from 2,631.15 baht per rai per year to 3,338.22 baht per rai per year (an increase of 707.07 baht per rai per year, or 26.87%), and their net income from selling
dry-season rice increased from 1,675.51 baht per rai per year to 1,840.56 baht per rai per year (an increase of 165.05 baht per rai per year or 9.85%).
In addition, it also helps reduce conflicts over water use in the area.
However, for sustainable development, farmers in the area should hold regular meetings of their water user groups.This is to ensure efficient water management and the ability to adjust water allocation plans promptly, in order to maximize benefits for the group members.

News : Public Relations / Information : Evaluation Center

Tha Maka Irrigation Canal Improvement Project, Phase 5, Benefits 40 Farming Households, Increasing Production and Income.
Scroll to top

เราใช้คุกกี้เพื่อพัฒนาประสิทธิภาพ และประสบการณ์ที่ดีในการใช้เว็บไซต์ของคุณ คุณสามารถศึกษารายละเอียดได้ที่ นโยบายความเป็นส่วนตัว และสามารถจัดการความเป็นส่วนตัวเองได้ของคุณได้เองโดยคลิกที่ ตั้งค่า

ตั้งค่าความเป็นส่วนตัว

คุณสามารถเลือกการตั้งค่าคุกกี้โดยเปิด/ปิด คุกกี้ในแต่ละประเภทได้ตามความต้องการ ยกเว้น คุกกี้ที่จำเป็น

ยอมรับทั้งหมด
จัดการความเป็นส่วนตัว
  • เปิดใช้งานตลอด

บันทึกการตั้งค่า